|
ANNEXE 1
Report
on
The Holyrood Project
to
The Scottish Parliamentary Corporate Body
by
John D Spencely
March 2000
Index
1. Introduction
2. My Terms of Reference
3. The Chronology of the Project
4. Review of the current estimates of
cost
5. Review of the current estimate of
time to delivery and occupation
6. Review of the value for money of
the project
7. Review and comparison of the advantages
of alternative contractual methods
8. Review of the effect on cost and
delivery of a reduced specification
9. Review of the effectiveness of communications
between the Corporate Body and the Project Team with recommendations
10. Report on the current market value
of the Holyrood site
11. Report on expenditure to date
1 Introduction
1.1 I was appointed by the Scottish Parliamentary Corporate Body on
25 February 2000, in accordance with the Terms of Reference 1 - 5
as set out in section 2 below, to report by 27 March 2000. Terms of
Reference 6 and 7 were added during the course of the Review and I
was also asked to make recommendations under all Terms of Reference
and to consider options for future action as I thought fit. This is
my Report.
1.2 I appointed, with the Corporate Bodys consent, Neil G Thomson
Chartered Quantity Surveyor and Robert B Wilson Chartered Architect
and Director of Estates of the University of Glasgow as my Advisers.
1.3 My Review has been carried out over a three week period by me
and my two Advisers. We have interviewed each member of the Corporate
Body, members of the Project Team and the Design Team and representatives
of the Construction Manager, all of whom have been very helpful. We
have been given access to reports and minutes of some Project and
other meetings and have inspected the work in progress in the Architects
Edinburgh office and on site.
1.4 I am conscious that, in the very short time available, my appreciation
of the detail of the Project can only be a fraction of that held by
those who have been involved for the past two years or so. Nevertheless
my Advisers and I have independently each come to similar conclusions
as to the condition of the Project. These conclusions form the basis
of my Report.
1.5 The creation of a building to house the Nations Parliament
is a great enterprise. Those engaged in bringing this Project to fruition
are working in a situation and on a building which are unavoidably
more complicated than most, if not all, have ever experienced. Little
in their previous experience can have prepared them for this task.
We found an enthusiasm and dedication to the project at all levels,
tempered somewhat by the stresses and strains of recent events.
1.6 Nevertheless my appointment by the Corporate Body indicated that
all might not be well with the Project and my Review confirms this.
1.7 It would have been impossible for me to have fulfilled my Terms
of Reference without the help of the Valuation Office Agency on whose
professional advice I have relied in respect of the site value and
the Construction Manager on whose programming skills I have relied
on in assessing a likely completion date.
1.8 I owe special thanks to my Advisers without whose skilled assistance
my task would have been impossible and to whom I am accordingly greatly
indebted.
1.9 In this Report, the "Client" means the Scottish Parliamentary
Corporate Body; the "Project Team" means the Clients
Project Sponsor, Project Managers and their team; the "Design
Team" means the Architect, the Engineers, the Quantity Surveyor
and other design consultants; the "Construction Manager"
means Bovis.
1.10 My Report is provided to the Corporate Body to assist with its
review of the Holyrood Project. The estimates for the building and
fit-out costs have been provided by, or derived from information provided
by, the Quantity Surveyor and the Project Team. The expenditure figures
have been provided by the Project Team. I have not independently measured
the area of the building. I have not made any independent estimates
of, nor made market enquiries about, building or fit-out costs. I
have not made any independent check of the expenditure figures.
1.11 My views on the scope for potential changes to the costs of the
building and fit-out are based on my understanding of the current
proposals of the Design Team and the Project Team.
1.12 The actual potential for real and achievable changes is a matter
for the Project Team and the Design Team based on their knowledge
of the Project. Any confirmation of the budget or establishment of
a new budget for the Project is a matter for the Client based on advice
from the Project Team and the Design Team. Any approvals by the Client
of design or design changes and any approval of expenditure estimates
should be based on advice given to the Client by the Project Team
and the Design Team.
John D Spencely
MA BArch DipTP RIBA PPRIAS MRTPI FCIArb
24 March 2000
2 My Terms
of Reference
My terms of reference are as follows:
1 To review the current estimates of cost and time to delivery and
occupation
2 To review the value for money of the Project
3 To review and compare the advantages of alternative contractual
methods
4 To review the effect on cost and delivery of a reduced specification
5 To review the effectiveness of communications between the Corporate
Body and the Project Team
6 To report on the current market value of the Holyrood site
7 To report on expenditure to date
and to make recommendations and consider options for future action
as I think fit.
3 The Chronology of the
Project
3.1 The Holyrood site was selected in January 1998.
3.2 The Brief was produced in April 1998.
3.3 The Architect was appointed in July 1998.
3.4 The Architects Outline Proposals were presented to the Client
in October 1998.
3.5 The Brief was revised by the Client during the Outline Proposals
work stage.
3.6 The Architects Scheme Design, which accommodated the changes
to the Clients Brief, was presented to the Client in March
1999.
3.7 Responsibility as Client for the project passed from the Secretary
of State of Scotland to the Scottish Parliament on 1 June 1999.
3.8 On 17 June 1999, the Scottish Parliament agreed the following
motion:
That the Parliament endorses the
decision to provide its permanent home on the Holyrood site and authorises
the Scottish Parliamentary Corporate Body to take forward the project
in accordance with the plans developed by the EBMT/RMJM design team
and within the timescale and costs estimates described in the Presiding
Officers note to members of 9 June 1999.
3.9 The Scheme Design was never approved by the
Client but the Design Team was instructed to proceed with detailed design
in July 1999.
3.10 A value engineering (cost reduction) exercise was carried out in
the summer and autumn 1999 by the Design Team. In October 1999 the Design
Team was instructed by the Client to change the shape of the Debating
Chamber and did so.
3.11 In November 1999 the Design Team was instructed by the Client to
implement some of the potential design changes identified in the value
engineering exercise, and to carry out a feasibility study on accommodating
203 additional staff.
3.12 In February 2000 the Design Team reported on the changes to the
design necessary to accommodate the additional staff.
3.13 In March 2000, after the commencement of my Review, the Design
Team was instructed by the Client to investigate the potential for reducing
the size of the building and the quality of the specification in order
to reduce the cost of the building.
4 Review of the current estimates of cost
4.1 This section reviews the history of cost reporting for the Project
and provides, at paragraph 4.5 below, an estimate of the cost of the
Project as I believe it actually stood in February 2000.
Costs have been reported throughout this Project under two main headings:
- basic construction cost
- fit-out and other costs
The fit-out cost and other costs
includes professional fees, VAT, site acquisition costs, demolition
and furniture, fittings and other
equipment not included in the basic construction cost.
4.2 The basic construction cost
4.2.1 10 separate cost reports, from the original site comparison
cost completed in December 1997 to the last feasibility cost check
on the plans current as at February 2000, have been produced by the
Quantity Surveyor. A value engineering exercise carried out in
the summer and autumn of 1999 by the Design Team culminated in a report
submitted to the Project Sponsor in October 1999.
4.2.2 These cost reports have been examined and the level of drawing
and specification information available at each stage for
costing has been established in discussion with the Quantity Surveyor.
4.2.3 The following table has been produced in order to plot the movement
of the basic building cost over the last two years. A
commentary follows.
| Breakdown
of |
|
Site
|
|
Yardstick
|
Stage C
|
|
Interim
|
|
Interim
|
|
Stage D
|
|
Stage D
|
|
Interim
|
|
Interim
|
Interim
|
| Buildings/elements |
|
Comparison
|
Costs
|
|
Cost
|
|
Cost
|
|
Cost
|
|
Cost
|
|
Cost
|
|
Cost
|
|
Cost
|
Cost
|
|
|
|
DEC '97
|
|
23/10/98
|
|
03/11/98
|
|
11/02/99
|
|
04/03/99
|
|
26/03/99
|
|
25/05/99
|
|
30/08/99
|
|
27/09/99
|
14/02/00
|
|
|
|
£M
|
|
£M
|
|
£M
|
|
£M
|
|
£M
|
|
£M
|
|
£M
|
|
£M
|
|
£M
|
£M
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Assembly
Block |
} |
44.93
|
} |
53.30
|
} |
53.98
|
} |
57.36
|
} |
54.70
|
} |
54.38
|
} |
54.61
|
} |
66.53
|
|
48.74
|
63.41
|
|
|
} |
|
} |
|
} |
|
} |
|
} |
|
} |
|
} |
|
} |
|
|
|
|
| MSP
Block |
} |
|
} |
|
} |
|
} |
|
} |
|
} |
|
} |
|
} |
-
|
|
20.54
|
22.98
|
|
|
} |
|
} |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Queensberry
House |
} |
|
} |
|
|
2.17
|
* |
1.79
|
* |
1.79
|
* |
1.79
|
* |
1.81
|
* |
1.86
|
* |
5.98
|
10.34
|
|
|
} |
|
} |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Car
park |
|
} |
|
} |
|
|
2.09
|
|
2.42
|
|
2.72
|
|
3.12
|
|
3.45
|
|
5.22
|
|
6.50
|
6.89
|
|
|
} |
|
} |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| East
Basement |
} |
|
} |
|
|
Incl.
|
|
incl.
|
|
Incl.
|
|
incl.
|
|
incl.
|
|
incl.
|
|
7.62
|
8.30
|
|
|
} |
|
} |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Site
dev/prep. |
} |
|
} |
|
|
1.54
|
|
1.83
|
|
1.85
|
|
1.85
|
|
2.29
|
|
2.79
|
|
4.97
|
3.36
|
|
|
} |
|
} |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Preliminaries |
} |
|
} |
|
|
7.47
|
|
incl.
|
|
Incl.
|
|
incl.
|
|
incl.
|
|
incl.
|
|
incl.
|
incl.
|
|
|
} |
|
} |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Externals |
|
} |
|
} |
|
|
Incl.
|
|
incl.
|
|
Incl.
|
|
incl.
|
|
incl.
|
|
incl.
|
|
incl.
|
incl.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Sub
total |
|
|
44.93
|
|
53.30
|
|
67.25
|
|
63.40
|
|
61.06
|
|
61.14
|
|
62.16
|
|
76.40
|
|
94.35
|
115.28
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Enhancement |
|
-
|
|
-
|
|
-
|
|
-
|
|
3.11
|
|
4.13
|
|
4.13
|
|
7.39
|
|
incl.
|
incl.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Contingencies
& |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Design
Reserve |
|
4.50
|
|
5.36
|
|
6.78
|
|
6.34
|
|
6.43
|
|
6.53
|
|
5.22
|
|
8.38
|
|
17.19
|
19.34
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Design
risk |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Assessment |
|
-
|
|
-
|
|
-
|
|
17.03
|
|
17.28
|
|
16.16
|
|
15.86
|
|
21.70
|
|
incl.
|
incl.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Art |
|
|
0.10
|
|
0.25
|
|
0.25
|
|
0.25
|
|
0.25
|
|
0.25
|
|
0.25
|
|
0.25
|
|
0.25
|
0.25
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Site
costs |
|
|
-
|
|
-
|
|
-
|
|
-
|
|
-
|
|
-
|
|
1.58
|
|
1.58
|
|
3.59
|
3.62
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Special |
|
|
-
|
|
-
|
|
-
|
|
0.14
|
|
0.14
|
|
0.14
|
|
incl.
|
|
incl.
|
|
incl.
|
incl.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| TOTAL |
|
|
49.53
|
|
58.91
|
|
74.28
|
|
87.16
|
|
88.27
|
|
88.35
|
|
89.20
|
|
115.70
|
|
115.38
|
138.49
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Gross
area |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| ex
car park m2 |
|
16,470
|
|
21,299
|
|
21,396
|
|
22,905
|
|
23,098
|
|
23,214
|
|
23,214
|
|
27,329
|
|
27,329
|
29,579
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Car
Park m2 |
|
3,600
|
|
3,300
|
|
3,300
|
|
3,736
|
|
3,867
|
|
3,867
|
|
3,867
|
|
3,792
|
|
3,792
|
1,731
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Total
Gross area m2 |
|
20,070
|
|
24,599
|
|
24,696
|
|
26,641
|
|
26,965
|
|
27,081
|
|
27,081
|
|
31,121
|
|
31,121
|
31,310
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* These figures excludes
M&E costs which are in the Main Building figures
|
|
|
|
|
|
4.3 Commentary on cost reports
4.3.1 The first cost estimate produced was part of the cost comparison
of Holyrood with other sites. It was based on a notional design produced
in December 1997. The basic construction cost was estimated at approximately
£50 million for a gross building area of 20,070m2. The balance area
(for circulation, plant rooms etc) used in the brief calculation was
20% of net area; this has proved to be an underestimate.
4.3.2 Once the design team was appointed yardstick costs were produced
by the Quantity Surveyor based on average rates for the different
types of accommodation and in October 1998 a new cost estimate of
£58.9 million was produced.
4.3.3 The winning concept design was developed in more detail over
the next 6 months, culminating in the Stage D cost estimate of 25
May 1999 of £89.2 million for a gross floor area of 27,081 m2 (including
approximately 40% balance area).
4.3.4 An amended budget of £62 million was approved in June 1999 based
on this estimate. This excluded the design risk assessment (i.e. design
uncertainty) and other costs totalling £27.04 million which had been
included in the £89.2 million estimate but which were not identified
in cost terms in the report to the Client.
4.3.5 Area and cost estimates produced in August and September 1999
showed a substantial increase in gross floor area to 31,121 m2 and
a rise in the basic construction cost to £115 million.
4.3.6 The value engineering exercise was conducted with the target
of achieving 25% savings. Potential reductions of £20 million in the
basic construction cost were identified of which £13.3 million were
accepted by the Client.
4.3.7 The area and cost estimates produced by the Quantity Surveyor
in February 2000 showed a further rise to a basic construction cost
of £138.49 million for 31,310 m2 gross floor area. These estimates
were based on the Feasibility Study prepared by the Design Team to
show how 203 additional staff could be accommodated. The reliability
of the cost estimate is uncertain, in my opinion, due to the short
time within which it was made and the limited information on which
it was based. Although the total gross area was only up by 200 m2
from the September 1999 figure, the (expensive) building area was
actually increased by 2,250 m2 partially balanced by
a reduction of (cheaper) car park area by 2,061 m2.
4.3.8 The effect of the changes to the Brief is that, in my opinion,
the Project design is less settled than it was in March 1999 and that
the estimate for the basic construction cost is less reliable than
it was in May 1999.
4.4 Fit-out and Other costs
4.4.1 In the latest report of February 2000 from the Quantity Surveyor
the costs excluded from the basic construction cost were as follows:
1. Site acquisition and associated costs
2. Building control and planning fees
3. Off site costs in respect of party wall disputes
4. Future legislative changes
5. Site and building investigation costs
6. Historic Scotland and archaeology contractor costs
7. Effect of discovery/excavation etc
8. Demolition costs
9. Hard and soft landscaping
10. Built furniture in MSP offices and Assembly and all internal furniture
and fittings, planting and equipment
11.Video Conference fit-out
12. Media room fit-out
13. IT hardware/equipment, data, video wall, video conferencing, telephones,
electronic voting etc
14. Official Building Models and wind tunnel testing
15. Inflation beyond March 1998
16. Professional consultants and Construction Management fees and
charges VAT
4.4.2 Project costs were reported to the Client in June 1999 showing
an original figure of £90 million and a revised figure of £109
million, as follows:
|
|
|
|
£ million
|
£ million
|
|
Site acquisition, demolition,
archaeology
|
5.0
|
5.0
|
|
Construction
|
|
|
50.0
|
62.0
|
|
Contingencies
|
|
|
5.0
|
6.0
|
|
Fees
|
|
|
|
10.5
|
14.0
|
|
VAT
|
|
|
|
12.0
|
14.0
|
|
Total site and construction
cost
|
82.5
|
101.0
|
|
Fit-out including loose furniture
& IT etc
|
|
7.5
|
7.5
|
|
Financial provision required
|
90.0
|
109.0
|
| It
will be seen that the fit-out budget was £7.5 million. |
|
|
4.4.3 As part of this Review the
Project Team has, at my request, updated the fit-out costs, which
include an allowance for contingencies, as follows:
|
£ million |
| Chamber |
2.00 |
| Committee Rooms |
1.50 |
| Catering Furniture |
0.50 |
| Reception Areas |
0.25 |
| MSP Block |
2.37 |
| Queensberry House |
0.44 |
| Towers/Canongate
|
1.10 |
| Miscellaneous |
2.31 |
| IT |
2.85 |
| Broadcasting |
2.63 |
|
15.95 |
| * Allowance for
Fees |
0.50 |
| VAT 17.5% |
2.88 |
|
|
| Revised
Total for Fit-out |
19.33 |
|
|
| Note:
*This is a provisional allowance for ad-hoc advice to the Project
Team. |
4.4.4 This revised total is incorporated
into the estimate of total budget requirements in section 4.5 below.
4.4.5 The base date used by the Quantity Surveyor for estimating basic
construction costs is March 1998. Cost estimates have to be adjusted
for the effects of inflation from then to the tender dates for the
various work packages so that the estimates may more closely reflect
what may happen to tender prices. Such adjustments have not so far
been applied to the cost estimates for this project. This Report does
so.
4.4.6 Any prediction for future inflation is naturally uncertain.
In the assessment of future costs contained in this Review, the Building
Cost Information Service indices
produced under the auspices of the Royal Institution of Chartered
Surveyors have been used. This produces a figure of 5% building inflation
from March 1998 to October 2001 which has been applied to the construction
cost in the estimate of total budget requirements below.
4.4.7 The site staff and accommodation costs of the Construction Manager
for any period beyond January 2002 have not so far been included in
any cost report. This Report does so.
4.5 Total Current Budget
Requirements
4.5.1 I believe that the total Project Budget requirement for the
scheme presented to the Client in February 2000 was as follows:
|
|
|
|
£ million
|
|
Site acquisition, demolition,
archaeology(including VAT)
|
5.00 |
|
Construction
|
|
|
126.00 |
|
Contingencies
|
|
|
12.50 |
|
Professional & Construction
Management fee
|
|
21.50 |
|
Construction Manager Staff Costs
(to January 2002)
|
2.24
|
|
Subtotal
|
|
|
|
167.24
|
|
VAT on £162.24 @ 17.5%
|
|
28.39
|
|
Fit-out (including VAT)
|
|
19.33
|
|
Inflation allowance from March
1998 on Construction Works to end of Tendering period
|
9.40 |
|
Construction Managers costs
Extended to Dec 2003
|
6.50 |
|
Total
|
|
|
|
230.86
|
I understand that VAT on Professional fees may be recoverable. If
this is the case, the total would be reduced by approximately £3.94
million to a total of £226.92 million.
4.6 Costs allocated to other budgets
4.6.1 Some costs associated with the Project are, and always have
been, covered by separate budgets. These include, for example, landscaping
works between the Holyrood site and the Queens Park and the
costs of the Project Team staff and their site accommodation. Such
costs are accordingly not included in any of the cost comparisons
in this Review. I understand that they have been reported to the Corporate
Body by the Project T
5 Review of the current estimate of time to
delivery and occupation
5.1 The most recent estimate of time to delivery and occupation prepared
by the Construction Manager (reference Bovis Programme dated 11 February
2000) was as follows:
| Delivery of building |
|
24 December 2002 |
| Occupation |
|
25 August 2003 |
5.2 Taking into account the current
state of the design and the current instructions to the Design Team,
I consider it unlikely that these dates will be achieved.
5.3 On the assumptions (provided by me to the Construction Manager),
that a new Scheme Design, including a cost plan, will be approved
by the Client by 8 June 2000 and that Bovis are appointed to manage
the fit-out as well as the basic construction, more realistic estimates
of time to delivery and occupation are as follows:
| Delivery of building |
|
25 August 2003 |
| Occupation |
|
24 December 2003 |
5.4 It is clearly imperative that the Brief is frozen now and that
the Design Team proceeds immediately to produce a Scheme Design including
a cost plan to a Brief and a budget approved by the Client, so that
approval may be given to proceed with the Project by 8 June 2000,
or earlier if that is possible. Removal of the current uncertainties
and a reduction in the overall Project cost could result in an earlier
date for delivery and occupation. These are matters for consideration
by the Client and the Project Team.
5.5 The MSP Block is programmed for completion in June-July 2002 and
Queensberry House in March-April 2003. I recommend that the Client
should consider taking
occupation of these two buildings in advance of the final project
completion date, for three reasons. They would otherwise lie unoccupied
which is bad for buildings; current MSPs would be able to occupy their
office accommodation before the next election; and the overall capital
cost of the project would be reduced by relieving the project of the
Construction Managers costs for maintaining the buildings unused
for up to 18 months. The resulting saving would accrue to the Client.
Early occupation would require the current location of the main plant
to be reconsidered, but I am advised that this would not be an insurmountable
problem.
6 Review of the value for money of the project
6.1 In this section, I set out some comparative costs for guidance
and follow this by a discussion on value for money.
6.2 Cost comparisons
6.2.1 The current estimate of the cost of the three principal elements
of the project, on a rate per m2 basis, is
| MSP Block |
|
£ 3,659m2 |
| Queensberry House |
|
£ 4,061m2 |
| Assembly/Debating Chamber |
|
£ 3,521m2 |
6.2.2 The MSP Block provides accommodation for MSPs and their support
staff. It may reasonably be compared with, on the one hand, high quality
Headquarters Buildings in Edinburgh and, on the other, Portcullis
House (the new accommodation for MPs at Westminster), as follows:
| MSP Block |
|
£ 3,659m2 |
| Headquarters Building |
|
£ 1,544m2 |
| Portcullis House |
|
£ 4,742m2 |
It will be noted that the MSP Block is estimated by the Quantity Surveyor
at a rate which is twice as expensive as an equivalent Headquarters
Building in Edinburgh, but about 75% of the cost of Portcullis House.
6.2.3 Queensberry House provides office accommodation for the Presiding
Officer and reception facilities for MSPs. I have been unable to find
an equivalent project for comparison. It will however be noted that
it is the most expensive part of the project, albeit the smallest,
and that it is nearly as expensive as Portcullis House.
6.2.4 The Assembly/Debating Chamber provides meeting rooms for the
committees of the Parliament, the Debating Chamber and support accommodation.
I have not found an exactly equivalent building in the UK and have
accordingly chosen to compare it with the newly completed Museum of
Scotland, simply because this is also a complex city centre building
with demanding structural and servicing requirements.
| Assembly/Debating Chamber |
|
£3,521m2 |
| Museum of Scotland |
|
£2,587m2 |
6.2.5 The fit-out costs of the Project have been calculated as a percentage
of the basic construction cost to allow the following comparison:
| Parliament |
|
13.3% |
| Headquarters Building |
|
16.0% |
| Museum of Scotland |
|
38.0% |
Information on Portcullis House is not included because the published
information is limited, and the Museum clearly has fit-out requirements
of a different order. The
comparison with the Headquarters Building favours the Parliament and
suggests that the fit-out standard is appropriate.
6.3 Comparison of basic construction costs
6.3.1 It may be helpful to show how these figures are built up.
TABLE 1
|
Comparative Analysis
: MSP Block
|
|
|
|
|
|
|
|
|
MSP Block
|
|
HQ Office
|
|
Portcullis House
|
|
Element
|
|
Rate/m2
|
|
Rate/m2
|
|
Rate/m2
|
|
|
|
|
|
|
|
|
Substructure
|
|
62
|
|
130
|
|
Incl
|
|
Frame Upper Floors
& Roof
|
)
|
|
)
|
|
)
|
|
|
Roof Finishes
|
)
|
1051
|
)
|
246
|
)
|
1178
|
|
Stairs
|
|
50
|
|
44
|
|
34
|
|
External Walls Windows
& Doors
|
|
1145
|
|
300
|
|
1723
|
|
Internal Walls &
Doors
|
|
243
|
|
50
|
|
396
|
|
Wall Finishes
|
)
|
|
)
|
|
)
|
|
|
Floor Finishes
|
)
|
|
)
|
|
)
|
|
|
Ceiling Finishes
|
)
|
265
|
)
|
165
|
)
|
307
|
|
Fittings
|
|
28
|
|
34
|
|
96
|
|
Services
|
|
720
|
|
475
|
|
1008
|
|
|
|
|
|
|
|
|
Preliminaries
|
|
95
|
|
100
|
|
Incl
|
|
|
|
|
|
|
|
|
Total Rate/m2
|
|
£3,659
|
|
£1,544
|
|
£4,742
|
6.3.2 In my opinion, the rates for the frame, upper floors and roof
finishes, the external walls and for the services would be worth reviewing
and the design and/or specification reconsidered if cost reductions
are to be pursued.
TABLE 2
|
ComparativeAnalysis:
Assembly/Debating
|
|
|
|
|
Assembly
|
|
Museum
|
|
|
Element
|
|
Rate/ m2
|
|
Rate/ m2
|
|
|
|
|
|
|
|
|
|
|
Substructure
|
|
155
|
|
156
|
|
|
Frame Upper Floors & Roof
|
)
|
|
|
|
|
|
Roof Finishes
|
|
)
|
869
|
|
425
|
|
|
Stairs
|
|
62
|
|
201
|
|
|
External Walls Windows &
Doors
|
|
765
|
|
584
|
|
|
Internal Walls & Doors
|
)
|
Incl
|
|
Incl
|
|
|
Wall Finishes
|
)
|
361
|
|
461
|
|
|
Floor Finishes
|
|
130
|
|
162
|
|
|
Ceiling Finishes
|
|
|
70
|
|
35
|
|
|
Fittings
|
|
98
|
|
Excl
|
|
|
Services
|
|
978
|
|
563
|
|
|
|
|
|
|
|
|
|
|
Preliminaries
|
|
33
|
|
Incl
|
|
|
Total rate/ m2
|
|
|
|
£3,521
|
|
£2.587
|
|
|
Total area/ m2
|
|
|
|
20,329 m2
|
|
12,803 m2
|
|
|
|
|
|
|
|
|
|
6.3.3 In my opinion, the rate for the frame, upper floors and roof
finishes would be worth reviewing and the design and/or specification
reconsidered if cost reductions are to be pursued. The rate for the
external walls may be explained by the complex building shape and
the rate for services by the sophistication of the communications
systems and security. They may be less open to review.
TABLE 3
|
Analysis of Queensberry House
|
|
|
|
|
|
|
|
|
Element
|
Rate/ m2
|
|
|
|
|
|
|
|
Repairs & Restoration
|
|
1724
|
|
|
Building Works
|
224
|
|
|
Wall Finishes
|
|
358
|
|
|
Floor Finishes
|
|
199
|
|
|
Ceiling Finishes
|
|
211
|
|
|
Fittings
|
|
134
|
|
|
Services
|
1211
|
|
|
Total Rate/ m2
|
£4,061
|
|
|
|
|
|
|
|
Total Area m2
|
|
2483 m2
|
|
6.3.4 The repairs and restoration element is clearly a considerable
burden on this part of the project. In my opinion, the rate for the
services is unusually high and would be worth reviewing and the design
and specification reconsidered.
6.4 Overall value for money
6.4.1 Value for money is in the eye of the beholder; in this case,
the Nation as expressed through the collective voice of Parliament
in debate.
6.4.2 If the current estimate of the Project cost, at £230.86 million
or thereby (see section 4.5.1 above), is accepted as accurate and
affordable, then no more need be said by me.
6.4.3 However, if Parliament were to decide that this is too great
a price to pay, but that the Project should proceed, then it may wish
to authorise a lesser sum on the Project.
6.4.4 I would counsel against setting cost limits on individual buildings.
The current design proposals for many parts of the Project have, I
consider, potential for reductions, and to set precise limits would
place unhelpful restrictions on the Project Team and disadvantage
the Project. I recommend that Parliament should go no further than
setting a limit for the Project as a whole and some guidance is given
in section 8 below.
6.5 Building area and overall quality
6.5.1 Turning now to the building, as opposed to the Project as a
whole, I observe that cost is the product of building area and building
quality. And that value for money is the perception of what one is
getting for ones money in absolute and relative terms. It is
possible to reduce the cost of a building by making it smaller and/or
by reducing the quality of materials and the quality and extent of
the built-in services and fit-out required for creature comfort and
support to the occupants.
6.5.2 Whatever quality is now thought to be appropriate in the light
of the reported costs, the Design Team has been working to meet the
requirement that "the building which the Scottish Parliament
occupies must be of such a quality, durability and civic importance
as to reflect the Parliaments status and operational requirements"
and that must clearly be kept in mind if costs are to be reduced.
6.5.3 The area of the building is a consequence of the number of people
working in the building and of the functions which they have to perform.
This is of course a matter for the Client.
6.5.4 On the assumption that staff displaced by reducing the size
of the buildings have to be housed elsewhere, the Client may wish
to consider, before taking a decision on size reduction, where they
would be housed and at what capital cost, if any.
6.5.5 Furthermore, it is the experience of all organisations, old
and new, that moving into a new building usually reveals that more
space is needed than had been
anticipated. It would, in my opinion, be imprudent to reduce the area
below the maximum that the site can contain, if this can be afforded.
6.6 Changing the site
6.6.1 I have considered whether or not a change of site for the Project
would be productive of savings in the present design. I have not considered
the merits of other sites.
This was not in my terms of reference. However the present state of
the Project has nothing, in my opinion, to do with the location of
the site.
6.6.2 Changing the site would mean starting again. A new brief would
be required as the precursor to a new design. The present design could
not, in my opinion, be
transplanted unchanged. Time would be lost and this would cost money.
The money invested in the Project to date would be largely thrown
away.
6.6.3 For these reasons and on the basis of the information currently
available to me, I consider that there would be no advantage in moving
this design to another site.
6.7 Queensberry House
6.7.1 In my opinion, the expenditure on Queensberry House, at an estimated
£10 - £11 million, is not value for money when compared with the benefit
gained. On the
information available to me, the building is in poor structural and
physical condition. In my opinion, the interior contains little of
architectural (as opposed to archaelogical)
value and the interior spaces are neither grand nor memorable. The
current design requires removing most of the fabric of the building,
and creating a conjectural 17th century
external appearance built around extensively repaired external walls.
The construction will be largely 21st century.
6.7.2 This is, in my opinion, an inappropriate approach to providing
Parliamentary accommodation, which can in any case only be achieved
at great expense in this building. It would, in my opinion, be more
appropriate and cost effective to provide the accommodation within
a building clearly of the 21st century.
6.7.3 Nevertheless, the current approach may be considered essential
and I appreciate that the design and design approval processes may
have reached a stage of finality which to undo might cause real harm
to the programme. If this is the case, the same effect could be achieved
at lesser cost by building anew from new foundations and I recommend
that this be done.
6.8 The MSP Block
6.8.1 In my opinion, the cost of the facades of the MSP block could
be reduced by simplifying the design. This would also make the facades
easier to build and reduce the frequency of maintenance, without compromising
the integrity of the architectural design. I recommend that this be
done.
6.9 Other issues
6.9.1 It has not been possible to review the value for money of other
elements of the Project within the time available. It will be clear
from the tabular comparisons contained in sections 6.2 6.3
above that there are significant variances from the costs of elements
of other comparable buildings and I recommend that these should be
borne in mind by the Client and the Design Team.
6.9.2 The terms of the agreements between the various members of the
Design Team and the Client and between the Construction Manager and
the Client are commercially confidential. I have studied them, but
as they are conventional, I do not think it necessary to subject them
to analysis in this review.
6.9.3 I do however observe that they were entered into on the basis
of a £50 million project. No doubt, had it been appreciated at the
time of entering into these contracts that the building costs might
increase to the levels now estimated, other terms might have been
agreed and the Parties may wish to consider this matter.
7 Review and comparison of the advantages of alternative contractual
methods
7.1 This section is about alternative contractual arrangements for
the building works. It is not about alternative methods of funding
the capital required for the Holyrood Project, which I have not been
asked to consider and which are, in my opinion, irrelevant to the
present situation.
7.2 The current contractual arrangement, which was selected before
the Design Team was appointed but confirmed as appropriate by the
Design Team, is as follows:
- The building works are divided into a series
of individual "works packages", each for a recognisable
element, such as "foundations", "frame", "electrical
services", etc.
- Each is put out to the market at the appropriate
moment, for suitable contractors to tender competitively. The most
economical is accepted and the work in that package proceeds. A
number of work packages will be in progress on site at any one time.
Clearly the work of individual work package contractors has to be
coordinated. A Construction Manager (Bovis) is employed by the Client
to do this.
- Each work package contractor is contracted
to the Client to carry out and complete his package in accordance
with the relevant drawings and specification.
7.3 This contractual arrangement may be contrasted with the "single
stage lump sum building contract", by which the carrying out and
completion of the entire building works are entrusted by the client
to a single "main contractor". The main contractor may (if
he so wishes and as would be normal) subcontract part or most of the
works to subcontractors. In this case, the main contractor and not the
subcontractor is responsible to the Client for carrying out and completing
the works in accordance with the drawings and specification. The main
contractor coordinates his own work with that of each of his subcontractors.
7.4 The principal reason for preferring the "construction management"
over the "single stage lump sum" contract is that the former
does not require the entire work for the whole building to be designed
and specified before any one "trade package" is let, whereas
the latter does.
7.5 Other things being equal, a building project will be completed earlier
by using the "construction management" method because building
can start earlier.
7.6 Subsidiary advantages of the "construction management"
method are as follows:
- The construction manager is engaged before
any building work starts and while design work is still in progress.
The Design Team can accordingly use his expertise in building techniques
to inform their detailed construction decisions, and his expertise
in programming construction operations to inform the selection of
appropriate work packages and the timing of design decisions.
- Because each work package is tendered separately
in a logical progression, any variance from the budget for a particular
work package can be compensated by increasing or reducing the content
of subsequent packages. This can provide a welcome degree of flexibility
to the Client and Design Team, albeit that this will diminish with
each successive work package.
- Furthermore, as each work package is tendered
separately, advantage of market conditions for each can be obtained
at the time it is tendered.
7.7 The advantages and disadvantages, by comparison, of the "single
stage lump sum contract" are a mirror image.
- In place of a speedier start on site, leading
to an earlier completion, the client obtains a greater degree of
cost certainty.
- In place of separate contracts with each trade
package contractor, the client obtains a single point of responsibility
with the main contractor.
- In place of the market price for each trade
package, the client has to pay the main contractors price
which is the aggregate of the cost of his own work and whatever
price he places on the work of his sub-contractors. The client does
not know what the subcontractor is being paid. In a fierce market
place, potential subcontractors may be subjected to a dutch auction,
forcing down their prices to the advantage of the main contractor.
The client will not benefit from the dutch auction but may suffer
from a reduced quality of management and workmanship by the subcontractor.
7.8 There are several contractual variants between the poles of "construction
management" and a "single stage lump sum contract" which
are not, in my opinion, relevant in the present circumstances. The question
which I therefore consider is whether it is advisable to change from
the present "construction management" method to a "single
stage lump sum contract".
7.9 A necessary precondition for a "single stage lump sum contract"
is a completed set of production information drawings and specification
before tenders for the works as a single package are obtained. I consider
the consequence of waiting for a completed set would be considerable
delay to the start, and therefore to the completion of the works.
7.10 The Project would lose the benefit of the expertise provided by
the present construction manager, and the knowledge of the Project which
he has accumulated since he was appointed in 1998.
7.11 Accordingly, I recommend that the contractual arrangements should
not be changed.
8 Review of the effect on cost and delivery
of a reduced specification
8.1 To reduce the settled specification for a project is to make a change.
Any change to a project has the potential to cause confusion (which
may lead to design error and/or uncoordinated design), delay and additional
cost. Most architects have had the experience of seeing changes instructed
to save money turning out unexpectedly to increase costs.
8.2 The timing of change is therefore critical.
8.3 In the Plan of Work adopted for this Project, the design programme
is divided into five work stages as follows:
Briefing
Outline Proposals
Scheme Design
Detailed Design
Production Information
8.4 In my opinion, this Project has not reached the end of Scheme Design.
Consequently, a reduced specification of materials should have the effect
of reducing cost more than the additional cost which might arise from
delay to the Project. Reducing the specification should, if it leads
to a simplification of the design of the building (in particular its
external appearance), also enable the building to be built more quickly.
8.5 To answer in another way, I suggest that any possible effect on
progress should not preclude consideration of a reduction in specification
if that were thought to be desirable for other reasons.
8.6 I have considered the scope for reducing the Project cost. This
is of course an exercise that can only be done knowedgeably by the Design
Team and the Project Team who are familiar with the Project design in
all its detail. I am confident from the discussions which have been
held with the Design Team and the Project Team that there is scope for
doing so and the cost comparisons in this Review support their view
that this is possible.
8.7 Such an exercise could, in my view, produce reductions in the order
of 15 20% from the current (February 2000) estimate of basic
construction cost and 10 15% from the current estimate of fit-out
costs. Achieving such reductions would produce the following results:
|
Target savings
|
£ millions
|
|
Building
|
20%
|
15%
|
|
Site acquisition,Demolition,
archaeology
|
nil
|
nil
|
|
Construction and
Contingencies
|
£27.70
|
£20.70
|
|
Fees
|
£4.30
|
£3.20
|
|
Construction Manager
|
Nil
|
Nil
|
|
VAT
|
£5.60
|
£3.20
|
|
Inflation
|
£1.90
|
£1.41
|
|
Extended programme
|
Nil
|
Nil
|
|
Fit-out
|
15%
|
10%
|
|
Gross reduction
|
£2.90
|
£1.93
|
|
Total reduction
|
£42.40 million
|
£31.44 million
|
Achieving one or other of these targets would produce a basic building
cost of £110.8 - £117.8 million and an overall Project cost of £188.46
- £199.42 million.
If VAT can be recovered on professional fees as previously mentioned,
a further £3.5 million in round terms could be saved from these figures.
9 Review of the effectiveness of communications
between the Corporate Body and the Project Team and recommendations
9.1 Conventional management structures and management processes for
a government funded project are in place. The Design Team has adopted
the industry standard "Plan of Work" for its design work.
9.2 Management Targets
9.2.1 Nevertheless the Project has acquired three characteristics
which these management systems are designed to prevent, as follows:
- The approved budget bears no relation to the
current Brief.
- The current Scheme Design bears no relation
to the approved budget.
The Project cannot be completed by the completion
date most recently reported to the Client.
9.2.2 Thus the Clients expectations for time and cost are not
being met.
9.3 Communications
9.3.1 There is an established route for communications between the
Corporate Body as Client and the Project Team.
9.3.2 Nevertheless the messages which are communicated are not always
understood and do not always lead to action being taken, when action
is clearly required. That the Clients expectations for time
and cost were not being met has been known within the Project Team
for nine months at least.
9.3.3 Messages are not always communicated along the established route
and line managers are accordingly, on occasion, less well informed
about decisions taken further up the line than those whom they are
employed to manage. This is clearly destructive of effective management.
In particular, messages between the Client and the Design Team do
not always pass through the Project Sponsor and Project Manager. This
has led to misunderstandings and to instructions not always being
acted on. I have observed examples of both of these during my brief
acquaintance with the Project.
9.4 Management recommendations
9.4.1 I do not consider that the characteristics to which I refer
above are the consequence of the management structure or the Plan
of Work procedures and I do not, accordingly, think that changes to
the structure or the procedures are essential. Nevertheless some changes
to the manner in which management operates would benefit the Project,
as follows:
- Those responsible for communicating a matter
on which a decision is required must ensure that the need for the
decision is spelt out in the communication.
- Those responsible for decision making must
allocate sufficient time to make and communicate decisions effectively
through the correct channel.
- Where matters are to be discussed and decisions
made at a meeting, the relevant line manager(s) should be present.
Thus, the Project Sponsor and the Project Manager should be present
at any meeting between the Client and the Design Team. The Project
Sponsor should be present at any meeting between the Client and
the Project Manager.
9.4.2 Although I do not consider it essential that the management
structure should be changed, it would nevertheless be prudent for
members of the Corporate Body to consider whether it has the time
and expertise to perform the Client role on a day-to-day basis. If
it does not think that it has, there are two options which could be
considered:
- Specialist member
Appoint one member of the Corporate Body as the principal link with
the Project Team, spending more time than any member of the Body
has yet been able to do and
becoming in the process better informed and more expert in Project
matters.
or
- Project Progressing Committee
Establish a Project Progressing Committee to support the Corporate
Body in the delivery of the Project. I leave consideration of who
should serve on this to the
Corporate Body.
In either case the responsibilities of the Project Sponsor should, in
my opinion, remain unchanged.
9.4.3 I recommend that arrangements are made to facilitate a closer
working relationship between the Architect and Engineers and the Quantity
Surveyor.
9.4.4 I recommend that the future design work of the Architects should
take place only in one office, rather than being geographically split.
10 Report on the current market value of the
Holyrood site
10.1 The site has been valued by the Chief Valuer for Scotland. His
valuations are based on what I consider to be reasonable assumptions,
but which have naturally not been market tested nor indeed checked with
the local planning authority. The determining factor is the investment
required for Queensberry House.
10.2 The Chief Valuer has provided three valuations for a mixed residential,
retail, office and hotel development of 25,000 m2, taking into account
the benefit of the work done on site and with three different assumptions
for Queensberry House, as follows:
Scenario 1: £5 million is spent on Queensberry House plus about £2 million
on professional fees, profit/risk, cost of finance and other ancillary
costs; no grant aid is available; the result is a £4 million loss on
the building, which has to be subsidised by the remaining development.
The current open market value of the entire site is estimated to be
between £8 million and £11 million.
Scenario 2: £11 million is spent on Queensberry House plus about £4
million on professional fees, profit/risk, cost of finance and other
ancillary costs; no grant aid is available; the result is a £12 million
loss on the building, which has to be subsidised by the remaining development.
(Note: the current Project estimate for
Queensberry House is £10 - 11 million).
The current open market value of the entire site is estimated to be
between £nil and £3 million.
Scenario 3: The full expenditure on Queensberry House is grant aided.
The current open market value of the entire site is estimated to be
between £12 million and £15 million.
10.3 If the local planning authority were to permit a development of
30,000 m2, these values are estimated as follows:
| Scenario 1 |
|
£10 million to £14 million |
| Scenario 2 |
|
£ 2 million to £ 6 million |
| Scenario 3 |
|
£14 million to £18 million |
10.4 However, neither the Chief Valuer nor I consider that it would
be prudent to assume that this greater area would be permitted by
the local planning authority and I recommend that it be discounted.
10.5 If accounting conventions for expenditure by the Parliament meant
that grant aid to Queensberry House was effectively a debit against
the Project, then Scenario 3 would not be relevant.
10.6 I should emphasise the tentative nature of these valuations.
They have had to be made without the normal enquiries and investigations,
in a very short space of time.
11 Report on expenditure to date
11.1 The expenditure set against the capital budget to date is shown
on the spreadsheet below. The total is £20.907 million.
|
|
|
£m |
£m |
£m |
|
|
|
|
ex
VAT |
VAT |
Inc
VAT |
|
| Site
acquisition |
|
4.000
|
|
4.000
|
|
| Demolition |
|
|
1.000
|
0.175
|
1.175
|
|
| Archaelogical
survey |
|
1.000
|
0.175
|
1.175
|
|
|
Sub-total |
|
6.000
|
0.350
|
6.350
|
6.350
|
|
|
|
|
|
|
|
| Fees |
|
|
All individual figures below
arecommercial-in- confidence
|
|
|
Bovis |
|
|
|
|
|
|
Bovis
(temp works) |
|
|
|
|
|
EMBT/RMJM |
|
|
|
|
|
RMJM
Services |
|
|
|
|
|
DLE |
|
|
|
|
|
|
OAP |
|
|
|
|
|
|
Buro
Happold |
|
|
|
|
|
Carillion |
|
|
|
|
|
|
Turner
& Townsend |
|
|
|
|
|
Lime
Centre Trust |
|
|
|
|
|
Sub-total |
|
8.006
|
1.401
|
9.407
|
9.407
|
|
|
|
|
|
|
|
| Work
Packages |
|
|
|
|
|
| 1610 |
Tower
cranes |
|
|
|
|
| 2100 |
Piling
& retention |
|
|
|
|
| 2200 |
Substructure
concrete |
|
|
|
|
| 2300 |
Earthworks |
|
|
|
|
|
|
Sub-total |
|
0.000
|
0.758
|
5.092
|
5.092
|
|
|
|
|
|
|
|
| Queensberry
House |
|
|
|
|
|
|
Various
works |
|
|
|
|
|
Sub-total |
|
0.011
|
0.002
|
0.013
|
0.013
|
|
|
|
|
|
|
|
| Site
preparation |
|
|
|
|
|
|
Store
stone |
|
|
|
|
|
|
Well
probing |
|
|
|
|
|
Well
drilling |
|
|
|
|
|
|
Sub-total |
|
0.038
|
0.007
|
0.045
|
0.045
|
|
|
|
|
|
|
|
|
Total |
|
|
|
|
20.907
|
11.2 The expenditure for March 2000 is expected to be around £3.5
million including VAT. The value of contracts let to and through Bovis
is £17,778,286 including VAT. This includes the value of contracts
let to or through Bovis for which payments have been made as shown
on the spreadsheet.
11.3 The contracts let do not represent committed expenditure. If
the Project were to be cancelled, the various construction and professional
contracts would, in general terms, entitle the contractors to reimbursement
of their earnings to the date of cancellation plus the reasonable
costs of closing down their various operations.
11.4 I cannot say what the costs of termination would be with any
degree of precision. Much would depend on when this was done and,
in my view, the manner in which it was done. However, if the Project
were cancelled in early April 2000, a budget for the costs incurred
as a result, including expenditure already incurred, would sensibly
be in the order of £27-£30 million.
11.5 Relating the site valuations to the predicted cancellation costs
shows that there would be a debit in the order of £16 - £30 million.
|